Battery Storage · Equipment Category

Power Conversion Systems

The converter sets the power rating, the fault behaviour and the grid services a storage plant can actually be paid for.

The PCS is where a battery becomes a grid asset

Cells store energy. The power conversion system is what turns that into something a grid operator will accept — it sets the power rating, the response time, the fault behaviour and, increasingly, the grid services the plant can be paid for. Two projects with identical batteries and different PCS platforms are not the same asset.

The significant change is that the PCS is no longer a commodity converter. Grid codes now require behaviours — ride-through, frequency response, reactive power at zero real power, and in some markets grid-forming operation — that live in the converter and its controls, not in the battery. Buying on cost per kilowatt alone selects against exactly the capabilities that determine whether the plant can be interconnected and what it can earn.

FamilyTypical configurationIndicative lead timeStandards
Central PCS SkidsUtility-scale conversion, usually skid mounted with the MV transformer as one deliverable. 1–5 MW per unit
630–800 V AC output
Outdoor rated
~38 weeks UL 1741 SB
IEEE 1547
IEEE 2800
String / Modular PCSMultiple smaller converters in parallel. Partial failure degrades output rather than losing a block. 100–400 kW per unit
Paralleled to block rating
Hot-swappable
~26 weeks UL 1741 SB
IEEE 1547
Grid-Forming PCSEstablishes voltage and frequency rather than following them. Required for black start and for weak-grid interconnection. 1–5 MW per unit
Virtual synchronous control
Black start capable
~44 weeks IEEE 2800
UL 1741 SB
ISO-specific
C&I Bidirectional InvertersBehind-the-meter conversion, frequently combined with solar input on a shared DC bus. 30–250 kW
480 V AC
Hybrid PV + storage
~16 weeks UL 1741 SA/SB
IEEE 1547
Rule 21
UL 1741 SB certification is interconnection-critical and product-specific. It certifies conformance to IEEE 1547-2018 grid support functions, and utilities increasingly will not process an application without it. Certification applies to a specific firmware and hardware combination — a field firmware update can invalidate it. Confirm the certified configuration matches what will actually be installed and operated. Lead times shown are indicative modelled positions for North America, reviewed monthly, published with their basis on the Equipment Lead-Time Index.

Specifications that decide the selection

Continuous rating at site conditions

Nameplate power is quoted at a reference ambient. Real derating at design-day temperature and site elevation can remove a meaningful fraction of it, and that is the number the plant actually dispatches.

Reactive capability at zero real power

Many interconnection agreements require reactive support when the battery is neither charging nor discharging. Not every converter can do it, and the ones that can may derate elsewhere to achieve it.

Grid-following or grid-forming

Grid-following converters need a stiff grid to synchronise to. On weak interconnections, or where black start is required, grid-forming control is not an upgrade — it is the entry requirement.

DC window versus battery voltage

The converter’s usable DC voltage range must cover the battery’s full state-of-charge range at the design C-rate. A mismatch quietly strands capacity at the ends of the range.

Selection criteria in practice

Typical applications

Utility-scale storage blocks pair a central PCS skid with an MV transformer, repeated across the site. Weak-grid and islanded projects, and any plant expected to black start, need grid-forming converters and the study work that goes with them. String PCS suits sites where availability matters more than capital cost, or where crane access is poor. Behind-the-meter commercial installations use bidirectional inverters, very often sharing a DC bus with rooftop or carport PV so a single conversion stage serves both.

Work the numbers before you specify

Related reading

Common questions

What is the practical difference between grid-following and grid-forming?

A grid-following converter measures the grid’s voltage and frequency and injects current in step with it — it cannot operate without a reference. A grid-forming converter creates that reference itself, behaving more like a synchronous generator. On a strong grid the difference is largely invisible; on a weak one, or during a black start, it is the difference between a plant that works and one that cannot energise.

Should the PCS and the battery come from the same vendor?

Integrated supply removes an interface and usually shortens commissioning, which is a real benefit. The cost is a longer commercial dependency: augmentation, spares and warranty all route through one party. Split supply preserves options but puts the controls integration risk on you, and that risk is not small.

How much oversizing is sensible?

Very little on the converter itself, but the derating at site conditions must be understood first — what looks like oversizing is often just the honest rating. Where genuine headroom is worth buying is in reactive capability, because interconnection requirements have tightened repeatedly and retrofitting that capability is expensive.

Does a PCS need its own protection, or does the MV switchgear cover it?

Both, and they must be coordinated. Converters current-limit rather than delivering a large fault contribution, so protection schemes designed around synchronous sources may not see a fault at all. This is a study question, and it needs to be settled before the switchgear relay settings are finalised.

Family reference pages

Each family below has its own page: how it is specified, the standards it is built to, its indicative lead time and market price band.

Working out a conversion rating?

Run the load and current numbers, then build the circuit from source to point of interconnection.

Open the calculators