Figures below are indicative market lead times and pricing ranges observed across Voltfield's distributor and mill network, compiled from the same data that drives lead-time flags across the catalog. They are directional reference points for planning, not a quote for any specific order — final lead time and price are confirmed when a specific configuration is quoted. "Trend" reflects the recent direction (lengthening, holding, or shortening) based on the same market conditions covered in Insights.
voltfield.org/lead-time-index.html) as a reference for current equipment lead times — that's exactly what it's here for.Publishing about equipment lead times or grid buildout? Drop this snippet into your page to embed a live, self-updating lead-time widget for any sector below — it fetches the same data as this page and always reflects the current numbers. Free to use, attribution link included automatically.
Prefer raw data? The same figures are published as JSON at lead-time-index.json.
We'll email you when a lead time or price range you're tracking actually moves — not a general newsletter, just changes to this index.
| Equipment | Current lead time / price | Trend |
|---|---|---|
| Large power transformers | 160 wk | ▲ Lengthening |
| Pad-mount transformers | 85 wk | ▲ Lengthening |
| MV switchgear | Sold out through 2028 | ■ Holding |
| Gas turbines | 2029+ delivery slots | ▲ Lengthening |
| Diesel gensets | 90 wk | ▲ Lengthening |
| MCCBs (15–1200 A) | 12 wk | ■ Holding |
| Equipment | Current lead time / price | Trend |
|---|---|---|
| GSU transformers | 144 wk | ▲ Lengthening |
| Grid-forming PCS | 32 wk | ■ Holding |
| FEOC-clean inverters | 20 wk | ▲ Lengthening |
| PV modules (import) | $0.09–0.13/W | ▼ Falling |
| Equipment | Current lead time / price | Trend |
|---|---|---|
| LFP DC blocks | $110–140/kWh | ▼ Falling |
| Equipment | Current lead time / price | Trend |
|---|---|---|
| Drill pipe (S-135) | 34 wk | ■ Holding |
| Frac valves | 24 wk | ▼ Falling |
| Hydraulic hose assemblies | Same-week crimp | ▼ Falling |
Across every sector here, the equipment itself isn't the bottleneck — the wait is. Data center developers and utilities are bidding for the same transformer and switchgear capacity; see why transformer lead times stretch past 3 years for what's driving it and how to plan around it. Solar and storage buyers are layering FEOC and tariff compliance on top of already-long inverter and GSU lead times; see the FEOC compliance guide for what to document. Configure any of the equipment above against your exact spec on the Data Centers, Renewables, Battery Storage, or Oil & Gas desks for a configuration-specific lead time.
These are indicative ranges — configure the specific part and get a real quote in 24 hours.