Data Centers · Equipment Category

Data center cable and busbar

The only line items priced substantially by weight of metal. Short lead times, commodity-linked pricing, and two sizing constraints that compete with each other.

The part of the estimate that moves with commodity prices

Cable and busbar are the only line items in a data centre electrical package priced substantially by weight of metal. That makes them behave differently from everything else: lead times are comparatively short, but pricing tracks copper and aluminium markets rather than manufacturing capacity, and a quote can go stale in weeks for reasons that have nothing to do with the supplier.

Two constraints govern the sizing, and they compete. Ampacity asks whether the conductor will overheat. Voltage drop asks whether the load still sees usable voltage at the far end. On short runs ampacity decides; past a few hundred feet voltage drop usually takes over and forces a larger conductor than heating alone would require.

FamilyTypical configurationIndicative lead timeStandards
MV Power CableMedium-voltage feeders between the utility interface, transformers and switchgear. 5 / 15 / 35 kV
#2 – 750 kcmil
EPR or XLPE insulation
~18 weeks ICEA, AEIC
UL MV-105
LV Power CableEverything downstream of the main switchgear. The highest-volume item on the site. #12 – 500 kcmil
THHN or XHHW-2
Copper or aluminium
~6 weeks UL 83, UL 44
Copper BusbarRigid conductor inside switchgear, PDUs and ground systems. 1/2in – 4in wide
1/8in – 3/8in thick
Bare or tinned
~10 weeks ASTM B187
Fibre Trunks & Patch PanelsStructured cabling between rows, halls and the meet-me room. OM3 / OM4 / OS2
12–144 fibre
LC / SC / MPO
~8 weeks TIA-568
UL 444
Aluminium is not simply cheaper copper. For the same ampacity it needs a larger conductor, which changes conduit fill, tray loading and termination hardware, and it requires terminations rated for it plus proper anti-oxidant treatment. On long feeder runs the material saving is real and routinely taken; on branch circuits and inside equipment it usually is not worth the handling. Lead times shown are indicative modelled positions for North America, reviewed monthly, published with their basis on the Equipment Lead-Time Index.

Specifications that decide the selection

Ampacity, after derating

Table ampacity assumes no more than three current-carrying conductors at 30 °C. Bundle more, or run hotter, and the usable figure drops — often sharply.

Voltage drop over the run

The 3 % branch and 5 % total guidance is a recommendation, not a hard limit — but it is what decides the conductor on any long run.

Insulation type and rating

XHHW-2 is rated 90 °C wet or dry; THHN is 90 °C dry, 75 °C wet. Underground and outdoors, that distinction is the whole decision.

Conduit fill

Capped at 53 % for one conductor, 31 % for two, 40 % for three or more. Fill is what usually forces a larger raceway, not the conductor itself.

Selection criteria in practice

Typical applications

MV cable runs from the utility interface to pad-mount transformers and MV switchgear. LV cable carries everything downstream — feeders to panelboards, branch circuits, mechanical loads. Copper busbar forms the rigid conductor inside switchgear and PDUs, and the ground bars that bond the room. Fibre trunks link rows to distribution frames and out to the meet-me room, sized well beyond current need because retrofitting is disproportionately expensive.

Work the numbers before you specify

Related reading

Common questions

Should I use copper or aluminium?

On long feeders, aluminium is routinely chosen and the saving is real. It needs a larger conductor for the same ampacity, terminations rated for it, and anti-oxidant treatment at joints. On branch circuits and inside equipment the handling penalty usually outweighs the material saving.

Which decides the conductor size, ampacity or voltage drop?

Both, and you have to check both. Ampacity generally governs short runs; past roughly a few hundred feet voltage drop tends to take over and force a larger conductor than heating alone would require.

Is the 3 % voltage drop figure a code requirement?

No. It appears as an informational note rather than a mandatory rule, so it is design guidance rather than something an inspector enforces. It remains the number most specifications are written against.

Why is conduit fill capped at 40 % for three or more conductors?

The limits exist for heat dissipation and for the mechanical practicality of pulling without damaging insulation. The single-conductor limit is higher because there is nothing else in the raceway to bind against or heat.

Family reference pages

Each family below has its own page: how it is specified, the standards it is built to, its indicative lead time and market price band.

Specifying cable or busbar?

Every family is in the Spec Library with its configuration axes, the standards it is built to, its indicative lead time and its market price band. Take the specification to whoever supplies it — Voltfield sells nothing and is not a route to any of it.

Browse cable specs ›