Data Center Power

How to Size a Standby Generator

A generator that can carry the running load can still fail the transfer. It has to accept the load in blocks, start the largest motor without collapsing the bus, and be rated for how long it will actually run. Here's the method, step by step, with a data center example.

By Voltfield Editorial Team·Published September 29, 2026·How we source & verify this
A diesel engine generator set on a skid
Diesel standby generator set (illustration)

Key takeaways

  • Size against four questions, not one: running load, block loading, largest motor start, and a rating valid for the actual run time.
  • Size on the UPS input, including losses and recharge, not the UPS output, and check motor starting with one set out (N+1).
  • Derate for altitude, ambient temperature and enclosure airflow, and pick the ISO 8528-1 rating that matches the duty.
On this page · 9 sections
  1. Step 1: Pick the right rating
  2. Step 2: Build the running load
  3. Step 3: Check block loading
  4. Step 4: Check the largest motor start
  5. Worked example
  6. Step 5: Derate for site conditions
  7. Step 6: Fuel and runtime
  8. Common mistakes
  9. Frequently asked questions

A standby generator is sized against four questions, not one. Can it carry the running load? Can it pick that load up in the blocks it will actually arrive in? Can it start the largest motor without an unacceptable voltage dip? And is its rating valid for how long, and how often, it will run? The running load is the easy part. The other three are where transfers fail.

Step 1: Pick the right rating

The same engine and alternator carry different published ratings depending on the duty. ISO 8528-1 defines them:

RatingWhat it assumes
Emergency standby (ESP)Runs only during outages, at variable load, for limited annual hours. The highest published kW.
Limited-time running (LTP)Constant load for a limited number of hours a year.
Prime (PRP)Unlimited hours at variable load, with an average-load limit.
Continuous (COP)Unlimited hours at constant load. The lowest published kW.
Data center (DCP)Added in ISO 8528‑1:2018 for data center duty. Manufacturers publish it as DCP or under their own names (DCC, for example).

A standby rating comes with conditions, typically a limit on average load over the run and on annual operating hours. The exact limits are set by the manufacturer, so read the rating definitions on the datasheet, not just the kW figure. For data centers this matters twice. First, a facility that treats the generators as its long-duration source is running them outside what "standby" assumes. Second, data center tier certification schemes generally expect generators rated to run without a runtime limit at the design load.

Step 2: Build the running load

List what the generators must carry after transfer, in kW:

Generators are rated in kW at 0.8 power factor, which fixes their kVA. A 2,000 kW set is a 2,500 kVA set. Check the load in kVA too, and watch for a leading power factor at light load, which generators tolerate poorly. The kW vs. kVA guide covers both.

Step 3: Check block loading

After an outage, load arrives in blocks as transfer switches close and equipment restarts. Each block causes a transient voltage and frequency dip while the engine governor and alternator regulator respond. Step-load acceptance, the largest block a set can take within its transient limits, varies widely with engine design. It's often what decides the generator size in a data center, rather than kW. ISO 8528-5 defines performance classes (G1 to G4) with progressively tighter transient limits. Specify the class, then check the manufacturer's step-load data against your actual blocks.

Timing matters too. NFPA 110 Type 10 systems must pick up emergency load within 10 seconds of an outage. Loads that aren't on the emergency system are usually sequenced in afterwards, with transfer-switch time delays, so no single step exceeds what the sets can accept. UPS rectifiers typically ramp their input up over several seconds (walk-in) rather than stepping it on, which softens the largest electrical block.

Step 4: Check the largest motor start

A generator is a much softer source than a utility transformer. Its short-circuit capacity is set by its subtransient reactance (X″d), typically a few times higher than a transformer's %Z. The same screening formula used in the Motor Starting Voltage Dip Calculator applies:

Dip ≈ LRkVA ÷ (LRkVA + source short-circuit kVA)   ·   Generator short-circuit kVA ≈ kVA ÷ X″d

Motors on drives or soft starters draw far less starting current than across-the-line starts. That's one reason modern chillers are rarely the problem they used to be. Harmonic distortion is also worse on a generator bus for the same reason, covered in the harmonics guide.

Worked example

A data hall with the following running load after transfer: 1,850 kW of UPS input (including recharge, from the UPS datasheet), 700 kW of mechanical load and 50 kW of building load, for 2,600 kW in total. Sets are 2,000 kW / 2,500 kVA with an assumed X″d of 0.15, in N+1.

For comparison, the same motor on a 2,500 kVA, 5.75% utility transformer (43,478 kVA short-circuit) dips the bus about 6.5%. Losing one generator makes the motor start worse than on utility power. That's the case to design for, not the all-sets-running case.

The assumptions: the X″d of 0.15, the load split and the across-the-line chiller start are illustrative. Use the alternator datasheet's X″d, your own load schedule, and the chiller's actual starting method. A drive-started chiller would make the motor check trivial.

Step 5: Derate for site conditions

Published ratings apply at reference conditions. At high altitude and high ambient temperature, engines lose output, and the manufacturer's derating curves say by how much. A generator room or enclosure also runs hotter than outdoors, and radiator airflow has to be checked at the site's design temperature, not the rating's.

Step 6: Fuel and runtime

NFPA 110 classifies emergency power systems by how long they must run at rated load without refueling: Class 2 is two hours, Class 48 is 48 hours, and so on. The class is set by the application and the authority having jurisdiction. Data centers commonly store a day or more on site. Fuel burn depends on actual load, so a set running at 43% burns far less per hour than at full load. The Generator Runtime Calculator works this out from the set's own consumption data.

Common mistakes

Frequently asked questions

How do I size a standby generator?

Choose the rating that matches the duty, add up the running load in kW (UPS input, mechanical and building load), then check it in kVA. After that, check the largest load block against the set's step-load acceptance, the largest motor start against its voltage dip, and derate for altitude and temperature. Size for the redundancy case with one set out.

What is the difference between standby and prime generator ratings?

A standby rating assumes the set runs only during outages, for limited annual hours and at a limited average load, which is why it's the highest kW figure. A prime rating allows unlimited hours at variable load. The same machine carries both, and the right one depends on how the site will actually use it.

What is generator step load acceptance?

It's the largest block of load a generator can pick up at once while keeping voltage and frequency within its transient limits. It varies widely with engine design, and in data centers, where cooling restarts in large blocks, it's often what decides the set size rather than running kW.

Why is a generator rated at 0.8 power factor?

It's the industry convention for three-phase gensets. The engine limits real power (kW) and the alternator limits apparent power (kVA), and stating kW at 0.8 power factor fixes the relationship: a 2,000 kW set is a 2,500 kVA set.

Next steps

The Data Center Backup Power reference covers the diesel, natural-gas and turbine generator families, and Genset Components covers the engines, alternators, controls and fuel systems inside them. The POD & Skid Designer checks a power block's generator capacity against a target load and redundancy level.

Equipment

Share this guide:
Cite or link to this guide

Free to quote with attribution. Suggested citation: Voltfield Editorial Team, “How to Size a Standby Generator,” Voltfield, updated September 29, 2026. https://voltfield.org/guide-generator-sizing.html

Get new guides by email

One short email when a new guide or calculator is published, at most once a month. Your address is used for nothing else.